- Math »
- Two pipes A and B can fill a tank in 16 hrs and 12 hrs respectively. The capacity of the tank is 240 liters. Both the pipes are opened simultaneously and closed after 2 hrs.
Two pipes A and B can fill a tank in 16 hrs and 12 hrs respectively. The capacity of the tank is 240 liters. Both the pipes are opened simultaneously and closed after 2 hrs.
Find out the remaining capacity of a 240-liter tank after pipes A and B are turned off following a 2-hour concurrent operation.
by Maivizhi A
Updated Mar 18, 2024
Two pipes A and B can fill a tank in 16 hrs and 12 hrs respectively. The capacity of the tank is 240 liters. Both the pipes are opened simultaneously and closed after 2 hrs. How much more water need to fill the tank?
After 2 hours, there are 170 liters of water still needed to fill the tank.
First, we need to find out how much water both pipes A and B can fill in 2 hours.
Pipe A fills 1/16 of the tank's capacity per hour. Pipe B fills 1/12 of the tank's capacity per hour.
So, in 2 hours:
- Pipe A fills 2 * (1/16) = 1/8 of the tank's capacity.
- Pipe B fills 2 * (1/12) = 1/6 of the tank's capacity.
Combined, both pipes fill: 1/8 + 1/6 = 3/24 + 4/24 = 7/24 of the tank's capacity in 2 hours.
Now, we need to find out how much of the tank's capacity is still left to be filled.
Initially, the tank needs 240 liters to be filled. In 2 hours, 7/24 of this capacity has been filled.
So, the remaining capacity to be filled is: 240 - 240 * (7/24) = 240 * (1 - 7/24) = 240 * (24/24 - 7/24) = 240 * (17/24) = 17 * 10 = 170
So, after 2 hours, there are 170 liters of water still needed to fill the tank.
Work and Time in Mathematics
Work and time problems in mathematics deal with determining the amount of work done or time required to complete a task, typically involving multiple entities working together or at different rates. These types of problems often involve the concept of rates, where the rate at which work is done or time is taken is measured in units of work per unit time (e.g., work per hour, work per day).
Here's a general approach to solving work and time problems:
-
Identify the Work to Be Done: Clearly understand the task at hand and what needs to be accomplished. This could involve completing a project, filling a tank, painting a wall, etc.
-
Determine the Rates of Work: Identify the rates at which each individual or entity can perform the work. This could be given in terms of work per unit time (e.g., items produced per hour, area painted per minute).
-
Set Up Equations: Use the rates of work to set up equations that represent the work done by each entity or individual. These equations often involve the concept that work done equals rate of work multiplied by time.
-
Solve the Equations: Solve the equations to find the unknowns, which could be the time taken to complete the task, the amount of work done by each entity, or any other relevant quantity.
-
Check Your Answer: Once you've found the solution, double-check to ensure that it makes sense in the context of the problem. For example, ensure that the time taken is reasonable and that the work done matches the requirements of the task.
Here's an example problem illustrating the concept:
Problem: If John can complete a job in 6 hours and Jane can complete the same job in 4 hours, how long will it take them to complete the job if they work together?
Solution: Let's denote the time taken by John to complete the job as t_J and the time taken by Jane to complete the job as t_Jane.
John's rate of work: 1/6 job per hour Jane's rate of work: 1/4 job per hour
When they work together, their rates of work add up:
Combined rate = 1/6 + 1/4 = 5/12 job per hour
Let t be the time it takes for them to complete the job together.
Using the formula Work = Rate × Time, we have:
Work done by John + Work done by Jane = Total work
(1/6)t + (1/4)t = 1
(5/12)t = 1
Solving for t, we get:
t = 12/5 hours = 2.4 hours
So, it will take John and Jane 2.4 hours to complete the job together.
Two pipes A and B can fill a tank in 16 hrs and 12 hrs respectively. The capacity of the tank is 240 liters. Both the pipes are opened simultaneously and closed after 2 hrs. How much more water need to fill the tank - FAQs
1. What are work and time problems in mathematics?
Work and time problems involve determining the amount of work done or time required to complete a task, often with multiple entities working together or at different rates.
2. How are rates of work determined in work and time problems?
Rates of work are typically given in terms of work per unit time, such as items produced per hour or area painted per minute.
3. What is the general approach to solving work and time problems?
The approach involves identifying the work to be done, determining the rates of work, setting up equations based on these rates, solving the equations, and checking the solutions.
Recent Updates
- Two ships are sailing in the sea on the two sides of a lighthouse. The angle of elevati...
- Aman’s salary is first increased by 25% and then decreased by 20%. The result is the ...
- P and S can complete a piece of work in 20 and 15 days respectively. They worked togeth...
- Each day that a library book is kept past its due date, a $0.30 fee is charged at midni...
- Teri goes shopping for some new clothes and then out to lunch with a friend. She spends...
- Two pipes A and B can fill a tank is 8 minutes and 14 minutes respectively. If both the...
- A and B stand at distinct points of a circular race track of length 135 m. They cycle a...
- The image of a candle flame placed at a distance of 30 cm from a mirror is formed on a ...
- In pea plants, Tall plant height is dominant over short plant height. If there are 200 ...
- A wall of length 10 m was to be built across an open ground. The height of the wall is ...
- A company contracts to paint 3 houses. Mr. Brown can paint a house in 6 days while Mr. ...
- In a forest 20% of Mushrooms are Red, 50% Brown and 30% White. A Red mushroom is poison...
- In a large population, 76% of the households own microwaves. A simple random sample of ...
- A bag contains 8 red marbles, 9 yellow marbles, 7 green marbles. How many additional re...
- Hugh bought some magazines that cost $3.95 each and some books that cost $8.95 each. He...